 Achievements 

Godawari Green Energy Limited has become the India’s first company to successfully commission the 50 MW concentrated solar power project at Jaisalmer under the phase 1 of JNNSM. The project has several achievements in terms of economies, society, recognition, operation and execution.

Execution

  • The project was commissioned within a record time of 29 months from the date of signing of PPA with the Government of India
  • First among the seven CSP developers under JNNSM to commission the project before time
  • GGEL project marks India on the world map for the green energy production
 

Energy for future

  • This plant reflects our commitment for a greener tomorrow
  • 110 million units of annual clean electricity generation
  • Reduction of 118,214 tonnes of CO2 every year

Empowerment

  • More than 600 jobs created over the last 2 years
  • 26,77,000 men hours of effort
  • Infrastructure development in nearby villages

Safety

  • No reported accidents during the development

Recognition

  • 2 CSP today awards
  • National geographic coverage in megastructures